Esten & Wetherby Street Water Project Update
With water lines this old—some over 100 years—it’s no surprise that unexpected issues come up during construction. The Department of Watershed Management (DWM) is actively working on Esten Street and has been in regular contact with Councilmember Bakhtiari, who continues to advocate for progress and accountability on behalf of District 5.
This project is part of a major effort to replace extremely old infrastructure—dating back to 1916—that has caused repeated problems for residents. While challenges have arisen throughout Phase I and more may come in the future, the work is moving forward. DWM may bring in additional resources to support Phase II to ensure the job gets done.
Below is a summary update provided by DWM:
Work continues to replace some very old lines, 109 years old. There have been lots of challenges throughout and will be some future issues ahead too - we may bring in additional resources to help for Phase II. Listed below is summary:
Per your request, below is the update for the 6-inch water main project on Esten Street SE:
Construction Project Report
Project Name: Esten Waterline Project – Phase I
Location: on Esten Street between Manigault and Wylie Street
Date: September 12, 2025
Project Description
The project involves replacing the 1916 wrought iron pipe with a 6-inch ductile iron pipe due to multiple recurring leaks and structural deterioration.
Phase I – Esten Waterline Project
Work Completed
Installed approximately 500 feet of 6-inch ductile iron pipe
Installed 12 water services
Installed 1 tee connection
Installed 2 – 45° bends
Installed 3 valves
Installed 1 new fire hydrant
Progress as of 9/12/2025
Pressure test – Complete
Chlorination test – Complete
Water services connected: 7 of 12 completed
Next Steps
Remaining service connections to be completed by 9/17/2025.
Once the contractor receives the Purchase Order (PO), mobilization will occur within 2 days.
Restoration activities (paving, landscaping, cleanup) are expected to take approximately 7 days, weather permitting.
Phase II – Weatherby Waterline Project
Project Description
The project will continue with installation of additional water infrastructure to improve reliability in the Weatherby service area.
Planned Work
Install approximately 500 feet of 6-inch ductile iron pipe
Install 13 water services
Install 1 tee connection
Install 2 – 45° bends
Install 3 valves
Install 1 new fire hydrant
Schedule
Phase II will be scheduled at a later date.
The community will be notified prior to work beginning to ensure minimal disruption.
Just know we are not going to stop until the job is done, we just facing a lot of water related problems here, we are on the path to move Atlanta forward.
Thank you Council Member Bakhtiari for your continued engagement with DWM.